City of Bartlett Water Valve Project Update:
The City of Bartlett will begin major improvements to the control systems of the City’s waterlines. These upgrades are designed to significantly reduce future unscheduled water outages and improve overall system reliability.
The City will continually to provide regular status updates on the state of the project as improvements are progressed.
This project is supported by the Texas Department of Agriculture Community Development Block Grant Program.
The project is expected to end on June 29th, 2026. Updates on the project progress will be published in the City's Alert Page and Facebook Page.
The City has made arrangements to distribute cases of water at City Hall during each scheduled interruption. The City will be distributing water any time during regular business hours, Monday through Friday, from 8:00 A.M. to 5:00 P.M. throughout the duration of the project.
Non-potable water will be accessible to the public at the Bartlett Volunteer Fire Department, located at 200 W. Clark St., Bartlett, TX 76511. This is a self-fill Station, bring your own water carrier.
We strongly encourage residents to make arrangements in advance and prepare accordingly.
Monday March, 3rd - Friday March, 6th Utility Outage Outage Schedule
Monday, 3/2/26
CITY-WIDE WATER OUTAGE starting at 8:00 A.M.
- Replacing valves at Emma/Jackson Street
- Replacing valves at SW Front Street/Pietzch Street
- Replacing valves at SE Front Street/Pietzch Street
Water will be turned back on after valves are replaced daily!
-----
Wednesday, 3/4/26
CITY-WIDE WATER OUTAGE starting at 1:00 P.M.
- Replace valves, multiple locations along West Elm Street
- Replace valve on West Jackson Street and prison tower
- Water will be turned back on after valves are replaced daily!
-----
Thursday, 3/5/26
CITY-WIDE WATER OUTAGE starting at 1 p.m.
- Replace valves at West Clark Street/Emma Street
We will push these updates out weekly throughout the project and do our absolute best to minimize the water outages to as few as possible. We thank you for showing grace to City Staff, our contractors and everyone involved during this project!
Please reach out to Adrian Flores at City Hall with any questions or concerns @ 254-527-3219 or Mayor Chad Mees @ 817-219-5160.